How does a swing set take two years to replace? Families who use the tot lot by Community Hall have asked that question since September 2024. That was when the park's original wooden swing set came out because of structural post rot.
The City used the removal to rebuild the ground under the swings, and the project has moved in stages: one contract for the site work, a second purchase for the equipment, and donor money from the Piedmont Beautification Foundation for the parts that children actually ride. Each stage waited on the one before it, which is why the swing area by Piedmont Park has stood empty for so long. The same foundation strings the lights on the 80-foot redwood a few steps away.
Pulling out a rotted swing set takes an afternoon. Replacing it to today's rules took far longer. A July 6, 2026 City Council agenda report says the City worked with the City Engineer on a plan to expand the swing zone for modern safety compliance and ADA accessibility, then set aside money already in the facilities capital budget before putting the job out to bid.
The work in that report reads more like a small civil project than a playground refresh:
The old set sat in sand inside a loosely defined area. The new one sits inside a built, drained, accessible enclosure. That enclosure needed design approval and a public bid before anyone could break ground, and that sequence accounts for most of the two years.
The City opened bids on June 18, 2026. Nineteen contractors bid, which is a lot for a job this size, and the bids varied widely.
| Figure | Amount |
|---|---|
| Lowest bid, Modernscapes Innovations | $156,364 |
| Highest bid, FBD Vanguard Construction Inc. | $289,300 |
| City engineer's estimate | $193,281 |
| Approved construction budget, with a 10% contingency | $172,000 |
The winning bid came in about $37,000 under the engineer's estimate. The highest bid was nearly double the winner. The Council awarded the contract to Modernscapes Innovations on July 6, 2026.
The money behind that $172,000 budget comes from two places. The City's Facilities Capital Funds cover $151,000, and the Piedmont Beautification Foundation covers $21,000. The swings themselves are not in that figure at all.
The Modernscapes contract specifically leaves out the swing equipment and the new ADA playground fiber surface. Those were to be bought and installed under a separate agreement with a certified playground equipment installer, through the state's California Multiple Award Schedule. The same report says the Piedmont Beautification Foundation, "as an early project supporter," raised the funds for the playground equipment. That equipment goes in right after the construction phase.
The City planned it as a relay:
An August presentation to the Park Commission showed what is going in: two bucket swings on colorful metal supports, set in ADA wood mulch.
When Parks and Projects Manager Nancy Kent briefed the Park Commission on September 2, the swing area was still closed "until the new bucket swings arrive," according to the meeting minutes. If you're planning a morning at the park around them, check the City's public works projects page for the current status before you head over.
The September minutes also cover work that most visitors will never notice. The heritage oak beside the play area had been standing in compacted sand. Crews air-spaded around the tree to loosen and remove that sand, then laid biochar to relieve the compaction.
A new planting area is already in, using California natives that have done well elsewhere in the city. The engineered wood fiber now covering the playground meets playground surfacing specifications and is ADA accessible. The benches will go back in.
That ties into a larger concern. In September the Piedmont Exedra reported on the City's Sustainable Parks Management Plan, which found that resident demand is outpacing what the city's landscapes can handle and flagged irrigation, stormwater, and slope stability as concerns. The swing project tackles several of those issues in one small corner, with new drainage, an oak freed from packed sand, and plantings chosen for how they hold up locally. It's a familiar story. Piedmont's new pool also had to adjust to demand after opening, and the city's off-leash dog areas depend on parks built for other uses.
The Piedmont Beautification Foundation is in its 62nd year. Its eight Trustees include three from the City, namely the Mayor, the Vice Mayor, and the Chair of the Park Commission, along with five from the Piedmont Garden Club. This year it also has 29 Advisors, including representatives of four other Piedmont garden clubs: Hoe and Hope, Highlanders Garden Club, East Bay Garden Club, and Home Gardeners. Patty Dunlap is serving her third year as president. According to the Exedra, no president had served three years since Barbara Magee, from 1987 to 1990.
Its next project will sit right beside the new swings. The Foundation's 2026 Spring Campaign is paying for a Nature Play Area. The foundation describes it as turning an underused part of the park into an outdoor learning space with climbing logs, native plants, and hands-on natural play elements. By September, more than $70,000 had been contributed and work was well underway at the main park Tot Lot. No opening date has been announced.
This isn't the Foundation's first playground. It gave $100,000 toward the new equipment at the renovated Linda Beach Tot Lot. Its regular giving also shapes the park around you. Commemorative trees cost $550 for a 24-inch-box tree or $1,300 for a 36-inch-box tree, and the City's Public Works project manager decides where they go. The commemorative bench program is paused because few suitable spots remain.
Every December, the City and the Foundation light the 80-foot redwood on the plaza in front of Piedmont Community Hall. The Foundation obtains, maintains, installs, and removes the tree's LED lights each year. The tree-lighting tradition dates to 1969. 2025 was its fourth year under the name Lights Up Piedmont!, which broadened it to include the light celebrations held by cultures around the world in midwinter.
The Exedra's preview of last year's event shows how many community groups take part. Piedmont Boy Scouts served hot cider donated by Piedmont Grocery and hot cocoa from Heafey Baum Group. Recreation Department staff served latkes donated by Chabad Jewish Center. Piedmont Girl Scouts ran light-themed crafts in the courtyard, and Santa took photos and letters inside the hall. After the Piedmont High School Troubadours performed, a Make-A-Wish recipient flipped the switch that lit the redwood, the menorah, Piedmont Park, and Community Hall.
The City's events calendar lists Lights Up! for Wednesday, December 2, 2026, at 7 p.m. The 2024 and 2025 celebrations started at 6 p.m. to suit young children, so confirm the start time as the date gets closer.
The Foundation is also bringing back its original Holiday Greeting Fund this fall. Neighbors donate in honor of one another, and the money funds City projects throughout the year. Details will be in a brochure arriving in November, and donor names and tributes will be published in early 2027. Around the 2024 lighting, the fund raised nearly $35,000, including $17,700 for replanting Dracena Park. The board chose this campaign after Parks and Projects Manager Nancy Kent outlined several City needs at its September meeting.
At Debbi DiMaggio, we love that Piedmont's most-used corners come from neighbors and volunteers working with the City over the long haul. If you'd like to talk about the parks, plazas, and traditions near the home you live in now or the one you're considering, we'd be glad to share what we know. Schedule your VIP consultation.
Debbi looks forward to learning how she might assist in all facets of your life—as a friend, a resource, and a partner in achieving your real estate goals. Whether you're renting, selling, buying, or investing, she's got you covered and is always grateful for the opportunity.